The question I get asked most often
is when will the building be finished? This blog is an update on where we are
at in answering that question.
Over the past few months, we've been
working under the assumption that we CAN and SHOULD finish construction of
Huntsman Hall in December 2015. At my request, in a meeting a few weeks ago, we
reviewed a detailed schedule of what has to happen in order to finish in
December. After reviewing the schedule, the contractor – and all of the rest of
us, including the business school contingent, USU facilities representatives,
the architects, etc., who need to support the contractor in order to achieve
that completion date – committed to finishing in December. This means that we
are moving forward with plans to use the classrooms starting in January 2016.
We also went through each critical
item that may prevent a December completion and discussed contingency plans on
how we can overcome any delays caused by those problems. To be honest, there
are a huge number of items that need to be done between now and then. On the
good side, the number of items is almost manageable!
Ken Snyder |
Note: I apologize about the vacation
my blog has taken the past few weeks. I've been in Japan with a group of MBA
students, and didn't really have the time to write.
Hi there,
ReplyDeleteI've read your blog, Really this blog is so informative it is totally based on business school, I like your blog. Thanks for sharing such type information.
Top Management Colleges in Greater Noida
Good Information.
ReplyDeleteThanks a lot for sharing this with us, was a really interesting post. and I want to share information about the
Ex-MBA Distance Education
Diploma in Mechanical Engineering Distance Education in Chennai